December 2022 – Update on October 2022 Post – £1.1M New Build
Building substantially complete to allow fitting of client equipment.
Building substantially complete to allow fitting of client equipment.
Cladding to roof & walls progressing with subsequent completion of [...]
Erection of steel frame and formation of machine pit & [...]
View of part placed suspended floors with client equipment foundations [...]
Sub-structure works continue on site – base walls to support [...]
Excavations & Trench Fill Commences on site.