July 2023
July 2023 – Update on February 2023 Post – £1M Extension to Existing Factory
Removal of asbestos roof covering and erection of temporary partition [...]
June 2023
June 2023 – Update on April 2023 Post – Fitting Out Extension to Existing Factory & External Works
Completion of External hardstanding areas.
April 2023
April 2023 – Update on March 2023 Post – Fitting Out Extension to Existing Factory & External Works
Demolition of internal dividing wall complete (70m long x 9m [...]
March 2023
March 2023 – Design & Project Management – £700K Fitting Out Extension to Existing Factory & External Works
JMPC is appointed by a large commercial business to design [...]
February 2023
February 2023 – Design & Project Management – £1M Extension to Existing Factory
JMPC is appointed by a large commercial business to design [...]
January 2023
January 2023 – Update on December 2022 Post – £1.1M New Build
External access ramps completed – building fully handed over.